PLEASE!! You only have a couple days to submit
comments to DEP about Longview.
BEFORE OR ON THIS SATURDAY, SEPTEMBER 2nd ! (Thanks to
those who have already sent letters! We need more!!)
Please ask the WV Dept. of Environmental Protection to deny the Draft
NPDES (discharge) permit for Longview. It’s hard to believe that a
company submitted such rubbish, and even harder to believe that DEP
approved it! We must require more of our regulatory agency. DEP is
merely going through the motions, and we must call them on it. We must
demand that the Department of Environmental Protection actually fulfills
the “protection” part of its name! I urge you
to pass this message along to anyone who may be interested.
The following is my letter to the DEP regarding the DRAFT water-discharge
permit. I ask that YOU please send a letter as well. Write your own
thoughts or feel free to plagiarize anything from the following letter,
Since my letter is a bit long winded (a bit hurried and a bit rude), here
are the main points I am trying to get across:
- The application form, the fact sheet, and the draft permit appear to
be for three different things. The application form states that 1.7
acres of land will be disturbed for a construction trailer and associated
parking. The fact sheet is for stormwater runoff from the
construction of a large power plant on 110 acres of land, and the
draft permit (issued by the DEP) is for the construction and
operation of a large power plant on 110 acres of land. Which is
it?
-
- The Operator or Contractor (Item 3) in the application is “to be
determined.” So DEP does not know to whom it is granting the permit?
-
- According to the application form, the Final Storm Water Management
Plan has “yet to be determined based on design.”
-
- So we have no operator and no design, yet we have a draft
permit.
-
- The Increase in Impervious Area (Item 16) in the application is not
consistent with a 600-megawatt coal-fire power plant.
-
- The gallons of water Longview says it needs in its permit application
is one half to one third the amount of water needed, according to other
documents and comments made by Longview elsewhere.
-
- Speaking of water, Longview claims it will have zero discharge.
That’s hard to believe.
-
Please send your comments to:
Director, Division of Water and Waste Management, DEP
ATTN: Michelle Brenner, Permitting Section
601 57TH St. SE
Charleston, WV 25304
***************************************************************************************************
August 30, 2006
Director, Division of Water and Waste Management, DEP
ATTN: Michelle Brenner, Permitting Section
601 57TH St. SE
Charleston, WV 25304
Subject:
NPDES Draft Permit No. WV0116238, Longview Power,
LLC
Dear Ms. Brenner:
I have reviewed the draft NPDES permit and associated application for
Longview Power, LLC, proposed to be built near Morgantown in Monongalia
County, West Virginia, and I have the following comments:
1.) It would be nice if a copy of all future correspondence
between Longview and the DEP could be placed in the Morgantown Public
Library. Charleston is a 3-hour drive each way from here, and if
Charleston is the only place the residents of Mon County can review
Longview’s applications and the many pages associated with them, then
that is an undue hardship on the people most affected by Longview. I
respectfully request that you require Longview to make an extra copy of
everything it sends to you, and I request that you send those copies
along with copies of your correspondence with Longview to the Morgantown
Public Library. The DEP’s Division of Air Quality did this for
Longview’s air permits.
2.) There are significant inconsistencies between the
information provided in the Site Registration Application Form, the
associated “Fact Sheet,” and the actual Draft Permit. I find it
difficult to believe that Longview filed an application with such errors,
and I find it even more difficult to believe that our own DEP actually
issued Longview a draft permit in the face of these glaring errors.
- a.) The number of Acres to be Disturbed (Item 5 in the
Application Form) is almost one tenth of the acreage in the Fact Sheet
and the Draft Permit. What is being permitted? 1.7 acres or 110
acres?
- b.) The description of the Project (Item 9 in the
Application Form) is for installation of a trailer and parking area. The
fact sheet is for construction of a 600-megawatt power station, and the
actual draft permit is for the construction and operation of a
600-megawatt power plant! Which is it?
3.) The information provided is woefully inadequate and
incomplete. The Operator or Contractor (Item 3 in the application) has
“yet to be determined.” Items 14 and 17 say that everything but the
construction trailer and parking area have yet to be designed! How can
the DEP grant a permit to someone they do not know for a project that has
yet to be designed?
4.) The Increase in Impervious Area (Item 16) in the
application is not consistent with a 600-megawatt coal-fire power plant.
The power plant and the land disturbed by it will result in an increase
of far more that 480 square feet of impervious area and 5 cubic feet per
second of discharge during peak storm events!
5.) Item 10 of the Fact Sheets states that Longview will
receive approximately 4,600 gallons per minute (gpm) of treated water
from a plant in Pennsylvania, and that will fulfill Longview’s cooling
needs. Everything else Longview has submitted states that treatment
plant will produce 7,000 gpm (see, for example, the report entitled
Use of Mine Pool Water for Power plant Cooling, prepared by
Argonne National Laboratory for the US Department of Energy’s National
Energy Technology Laboratory in September 2003). Longview has stated
elsewhere that the water produced by the mine-pool treatment plant
(approximately 7,000 gpm) will only be half of the water required by
Longview, if it were built. Therefore, Longview states in the NPDES Fact
Sheet that it will use approximately 4,600 gpm, but has stated elsewhere
that is needs 15,000 gpm. This is a huge discrepancy. The true amount
of water used by Longview must be clarified. The DEP must not allow
Longview to pull numbers out of the air, as it is clearly doing.
6.) No maps or plans were attached to the Application, Fact
Sheet, and Draft Permit that was given to my neighbor when he drove all
the way down to Charleston to get a copy of this permit and application.
Were these crucial pieces of information even submitted to the DEP by
Longview?
7.) I find it difficult to believe that there will be NO
water discharge. The statement that and extra water there is will be
used for “dust suppression” is troubling. It sounds as if Longview will
merely be land applying their water. I also don’t believe that Longview
will send its untreated water back to PA!! What will that water be like
after it has been through a cooling tower several times? In fact, I
would like to see more details on how Longview plans to reuse water
multiple times in its cooling fans. That water will be so mineralized
after one or two passes, it is difficult to believe it would be usable.
In addition, the water will be hot after one pass through. How can hot
water be used for cooling?
8.) There were no details on the water treatment plant
proposed for the site; in fact it was barely mentioned in the
application. There will be coal piles on site and other water runoff
that must be treated, yet there is no discussion of this on-site
treatment plant!
As with everything else Longview has submitted to date, this NPDES permit
application is a bait and switch tactic. Longview has repeatedly
submitted inaccurate and incomplete information to the State Regulatory
Agencies. This company has said one thing and done another throughout
the whole planning and attempted permitting process, and the DEP needs to
call them on it now.
I hereby request that the DEP deny Longview’s NPDES permit because
Longview clearly failed to provide information, ALL the information, in a
complete and accurate manner.
Sincerely,
Paula J. Hunt